New Home Construction Process in Belton, TX

A presentation screen displaying a line graph with an upward trend.

Planning Phase 90 - 120 days

  • Initial project meeting
  • Sign Design Agreement
  • Develop and finalize plans & Specs
  • Architectural approval is obtained
  • Pre–selection budgets
An L-shaped ruler with measurement markings.

Pre–construction phase 30 - 45 days

  • Sign Contract agreement
  • Close Construction loan
  • Pre–construction meeting
  • Build site 
  • preparation
Black construction hard hat.

Construction phase 8-12 Months

  • Foundation
  • Framing
  • Mechanical
  • Interiors build out
  • Ha
  • rdscape and landscape
Black house icon.

Closing Phase 2-3 weeks

  • Customer walkthrough orientation
  • Obtain certificate of Occupancy
  • Final Punch list
  • Close on home and move in